消息称为赶数据中心工期,Oracle 用卡车转运天然气应急

彭博社报道,Oracle 在犹他州一座数据中心已用卡车转运天然气超过一年,缓解燃气管网建成前的能源缺口。该方案还被导入为 OpenAI 建设的得克萨斯州 Shackelford 数据中心,并可能扩展到新墨西哥州的 Project Jupiter 项目。卡车转运需经压缩、运输、减压等步骤,成本约为管道输送的 4 倍,每辆拖车所载天然气仅够 100MW 数据中心运行 40 分钟。

Current read

Oracle 为了赶算力上线,直接用卡车拉天然气喂数据中心,成本是管道的4倍,一辆车只够烧40分钟,够野的。

11 sources63° AI heatLast updated 2026/10/9 02:54:44